Shutdowns & Revamps
Abu Dhabi, UAE
Replacement of shear machines and a pinch roll within a live rolling mill during a planned 28-day shutdown window, requiring precision sequencing across mechanical, structural and E&I disciplines.
Project Year
2026
Industry
Steel Manufacturing
Contract Type
Lump Sum
Project Value
Peak mobilisation: 65 personnel
Project Overview
ELGC was engaged to replace shear machines and a pinch roll within an operating rolling mill during a planned 28-day shutdown window. The project required precision sequencing across mechanical, structural and E&I disciplines to meet the fixed outage schedule.
The scope was executed by a peak workforce of 65 personnel working across parallel workfronts. Pre-shutdown preparation — including scope freeze, method statements and material staging — was completed before the window opened, enabling ELGC to begin heavy lifting on day one.
All equipment was replaced, aligned and reinstated within the planned window, with commissioning checks completed before handback to operations.

Technical Details
Client
Leading integrated steel producer (identity withheld)
Location
Abu Dhabi, UAE
Project Duration
28-day shutdown
Built-up Area
N/A
Structure Type
Industrial Structure
Business Unit
Shutdowns & Revamps
Scope of Work
Structural Modifications & Support Works
Equipment Replacement & Erection
Piping Re-routing
Electrical & Instrumentation Tie-ins
Multi-workfront Shutdown Management
Key Highlights
28-day shutdown window maintained
Peak mobilisation of 65 personnel across parallel workfronts
Scope freeze and workpacks completed before window opened
All disciplines — mechanical, structural, E&I — under single team
Equipment commissioned and handed back to operations within window